RETRA – Real Estate Transformation DE
Aerial view of the logistics and IOS site in Grimma with halls and outdoor storage areas

Reference project · Grimma, Leipzig district

Two-stage transformation of 30.5 ha of commercial and industrial land (GE/GI)

30.5ha
Plan area: commercial and industrial zone (GE/GI), special-use area (SO) and land for public facilities (day-care centre, fire station and assembly venue)
approx. 12ha
Expansion of the commercial site onto former agricultural land
135,000m²
of IOS space in the plan area enabled under planning law – on the existing site and the expansion areas

The role of RETRA

Project sponsor on behalf of the investor

In two stages, RETRA developed an established commercial site on the A14 motorway between Leipzig and Dresden for an investor: first by developing the existing site, then as project sponsor (Vorhabenträger) in the land-use planning process for 30.5 ha – with transaction and asset management from a single source.

Services
Deal sourcing and transaction management, land-use planning including coordination of the planning firm, expert reports and authorities, development including new construction, asset management
  • Sourcing – involved
  • Transaction – involved
  • Zoning – involved
  • Development – involved
  • Asset Mgmt. – involved
  • Hold/Exit – not involved
Top view May 2019: starting point Top view September 2020: earthworks Top view October 2020: surfaced areas Top view September 2021: areas in operation 05/2019
2019Starting point2021

Drag the slider or click a step

Stage 1 · Development

From storage yard to high-performance IOS site

Drag the slider to follow the development of the outdoor storage areas.

  1. 05/2019
    Starting point
    Unsurfaced storage areas next to the existing halls.
  2. 09/2020
    Earthworks
    Demolition, soil replacement and preparation of the subgrade.
  3. 10/2020
    Surfacing
    Load-bearing, surfaced outdoor storage areas for heavy loads.
  4. 09/2021
    In operation
    Fully used IOS areas with container and component storage.

Stage 2 · Land-use planning and expansion

From agricultural land to a commercial and industrial zone (GE/GI)

Left: the site before planning; right: the land-use plan – the newly designated areas in gold, with an example of possible IOS use featuring rows of containers, reach stackers and forklifts.

Schematic plan: existing site with agricultural land before planning Schematic plan: land-use plan with new commercial and industrial areas and IOS use
Before · Existing siteAfter · Land-use plan

Before · Existing site

  • Agricultural land
  • Plan boundary · 30.5 ha

After · Land-use plan

  • Newly designated areas (GE/GI)
  • Possible IOS use: containers (schematic)
  • Reach stackers and forklifts
  • Plan boundary · 30.5 ha
Schematic depiction based on the plan drawing · Geodata © GeoSN, dl-de/by-2-0

Land-use plan procedure

  1. 06/2023
    Resolution to draw up the plan
  2. Spring 2024
    Preliminary draft and early participation
  3. End of 2024
    Draft completed
  4. 03/2025
    Approval and public display
  5. 2025/2026
    In force